Habitat for Humanity Photos and Progress

Click photos for a larger view.

To the right is a photo of the house as of July 21. 
   
   

Below  are photos taken at the early stages of the build, before any digging took place.  Volunteer crews were able to build walls in advance, and a brief wall raising ceremony was held on Wednesday, July 8. 

 

During the week of July 22 to 25, the remaining windows and siding will be installed.  Then there will be about a three-week break to let the subcontractors install electrical, plumbing, and heating/cooling systems.  After the break, the workdays on this house will be Wednesdays and Saturdays.  On those days, we will be insulating, dry walling, painting and landscaping.  HFH hopes to have this house completed by the end of October. 

webassets/July09Build.JPG

   

webassets/IMG_3989.JPG

webassets/IMG_4001.JPG

webassets/IMG_3986.JPG

webassets/IMG_4004.JPG

webassets/IMG_3990.JPG